Bidirectional, Fast-Charging Stations Developed for Plug-In Electric Vehicles

A team of Burns & McDonnell engineers, along with subcontractor Coritech Services, has developed a system of bidirectional, fast-charging stations for a fleet of plug-in electric vehicles at Fort Carson, Colo. This first-of-its-kind system will push power back to the base microgrid when needed to meet installation demand or improve overall power quality.

SPIDERS bidirectional charger

On Aug. 29, the team successfully commissioned five bidirectional chargers and the aggregating control system as part of the Smart Power Infrastructure Demonstration for Energy Reliability and Security (SPIDERS) microgrid project at Fort Carson. Commissioning was performed using both Boulder Electric Vehicle and Smith Electric trucks, which are being provided for use on SPIDERS under separate agreements with the U.S. Army's Construction Engineering Research Laboratory (CERL) and Tank Automotive Research, Development and Engineering Center (TARDEC).

Commissioning of the vehicle charging stations represents an important milestone of the Fort Carson SPIDERS project, which is nearing completion. The project is managed by the U.S. Army Corps of Engineers (USACE), Omaha District, and includes technical guidance from CERL and TARDEC.

The bidirectional charging units are capable of providing up to 300 kilowatts (kW) of power to plug-in electric vehicles and also can discharge a like amount of stored energy from the vehicle batteries to the grid or microgrid via Society of Automotive Engineers (SAE) standard J1772-compliant bidirectional charging cables. The vehicle-to-grid (V2G) charging includes power factor correction, which is a growing concern at locations such as Fort Carson that are experiencing a growth in on-site solar power generation, resulting in utility rate penalties.

Each of the five chargers have been tested to charge and discharge at full capacity of 60kW, and have imported and exported a combined 394 kVAR (reactive power that diminishes the real power capacity of transmission lines) to the local grid even when electric vehicles are not connected to the chargers. This provides a 24-hour-per-day benefit to Fort Carson by absorbing VARs from the grid, thus increasing the power factor of the loads at Fort Carson and making the transmission of power from the local utility more efficient and less costly.

The chargers are also integrated into the SPIDERS backup power microgrid, which allows the installation to utilize a fleet of bidirectional-capable electric vehicles as energy storage devices that, in conjunction with diesel generators and a 2-megawatt (MW) solar photovoltaic array, increases the reliability and efficiency of backup power systems to critical facilities at Fort Carson. The Burns & McDonnell team also includes Southwest Research Institute (SwRI) and Intelligent Power & Energy Research Corporation (IPERC) that provided design, programming and aggregation of the vehicle charging solution and microgrid integration.

Tell Us What You Think

Do you have a review, update or anything you would like to add to this news story?

Leave your feedback
Your comment type
Submit

While we only use edited and approved content for Azthena answers, it may on occasions provide incorrect responses. Please confirm any data provided with the related suppliers or authors. We do not provide medical advice, if you search for medical information you must always consult a medical professional before acting on any information provided.

Your questions, but not your email details will be shared with OpenAI and retained for 30 days in accordance with their privacy principles.

Please do not ask questions that use sensitive or confidential information.

Read the full Terms & Conditions.